Project Photo Link     Project Progress Link     Bings Landing Team Members Link 

SR A-1-A NATIONAL SCENIC BYWAY, BINGS LANDING PROJECT

Project number FC 10-16

Flagler County Florida


bings.jpg (142704 bytes)

Location
click to see a larger image.

Site updated 7/29/11

This $172,325.00 dollar contract is for improvements to the Bings Landing  Intercoastal Waterway access area.

The contract time is 180 days for project construction. The project started on April 04, 2011.  The projected completion date is September 30, 2011 This date will change due to delays from weather, hurricanes, and unexpected delays.


SE Cline Construction Inc. is the general contractor.