February 24, 2005
Re:
Preconstruction Conference AgendaI-95 Widening and Reconstruction Flagler County
FIN: 242340-1-52-01 F.A.P. No.: 0954 119 I
242341-1-52-01 F.A.P. No.: 0951 559 I
Contract No.: T5071 I-95 Flagler County
A preconstruction conference was held on February 22, 2005 at 10:00 AM to discuss the above referenced projects. A list of attendees is attached. The following issues were discussed.
Introductions
The attendees introduced themselves.
Description of Project
Tom White read the following project description "This project consists of widening I-95 to the median from 4 to 6 lanes and milling and resurfacing the existing 4 lanes throughout Flagler County. The improvements also include reconstruction of the SR-100 interchange including full replacement of the existing bridge, replacement of the bridge over Pelicer Creek, and construction of the median storm water collections system including ditch bottom inlets and storm sewer pipe to convey storm water to proposed retention areas. Other improvements include outside widening to lengthen ramp acceleration lanes, milling and resurfacing of interstate ramps, and the reconstruction of SR-100 under I-95. Other activities include signing, pavement markings, and signalization
Contractor: Superior Construction Co Inc ;
Standard Bid Amount $ 73,163,37818 (A Bid)
Time Bid $ 11,200,00000 (B Bid)
Total Bid Amount $ 84,363,37818 (A+B Bid)
Contract Calendar Days 800 Days "
Important Dates
Tom White provided the project date information.
Project Award; December 20, 2004
Execution; January 11, 2005
Notice to Proceed; February 10, 2005 + 60
First Chargeable Contract Day will be: April 10, 2005 ;
Contractor’s anticipated start date: March 14, 2005
Delineation of Lines of Authority were established:
FDOT
Resident Engineer Michael Ruland Phone 386-254-3730
Project Manager Suzanne Phillips Phone 386-258-4449
·
Asphalt Specialist Tim McGlone Phone 386-258-4447RS&H CS
Senior Project Engineer Thomas White Phone 386-673-7801
Project Administrator William Downey Phone 386-673-7801
·
Contract Specialist Sean Heffernan Phone 386-673-7801·
Office Manager Deborah White Phone 386-673-7801Contractor
·
Project Manager Curtis Long Phone 904-545-8763·
Superintendent Fred Henning·
QC Manager Cynthia Kelly Phone (904) 292-4240·
Emergency Phone Numbers (Day and Night) are attached.
Utilities
Utility company comments were reviewed with the status of each utility
§
FPL: Mr. Bruce Stephenson provided an update of their relocation activity. They plan on being complete by March 14, 2005 Bruce noted the overhead wires will be deactivated at that time but may not be removed due to coordination with the FHP.§
Bellsouth: No one from Bellsouth was in attendance, however Steve Nunnery noted that they couldn’t complete their work until the new FPL poles are in place.§
Brighthouse: No one from Brighthouse was in attendance, however, Tom White noted they have installed their bores and plan to be clear before construction starts.§
City of Palm Coast: Steve Flanagan reported the jack and bores for the relocated water and sanitary lines have been installed. Testing and tie in connections remain. Steve asked if the new drainpipe at Old Kings Road could be located in order to avoid a conflict with their new line. Tom and Curtis will coordinate. Steve confirmed they would be relocated prior to March 14, 2005. It was noted the City has other crossings of the Interstate that should not be effected by construction, and no relocation is scheduled. The City is a part of the One Call System.Points of contact and phone numbers are attached to the minutes.
The Utility Representatives were excused.
Minority Programs by Willie Allen , Resident Compliance Officer
EEO Requirements
Labor Interview Requirements
Other Requirements (On-The –Job Training)
EEO Meeting
Beginning with Projects Let 2005; submit form 700-011-13 on a monthly basis the Friday prior to monthly estimate cut-off (See form for instructions)
Errors or Omissions in the Plans
Curtis Long noted there were no errors or omissions noted at this time with the exception of the open RFI issues.
Maintenance of Traffic Bill Downey outlined the MOT requirements.
Bill reviewed the lane closure restrictions; Sheet 244 and 519 of the MOT plans, 8:00 PM to 6:00 AM.
Curtis confirmed that Superior plans to utilize the MOT plans included in the contract.
It was noted the Certified Maintenance of Traffic (MOT) Review Report (DOT Form 700-010-08) was due at the progress meetings each week See Supplemental Specifications 102-14 for more details;
Curtis noted the name of ATSSA certified worksite supervisor, certification, 24 hour contact information were included in their package.
Bill called everyone’s attention to Spec 710-41- Reapply all traffic stripes and markings a minimum of 14 days after first application but prior to final acceptance of the project;
Bill noted there was a contract for on duty Law Enforcement officers for speed control, and he outlined how the off duty officers were utilized according to the contract.
Erosion Control and SW Pollution Prevention Plans Bill noted the following items were required:
Contractor Certification Forms (DOT Forms 650-040-05 and 650-040-07)
All permits must be posted on the project bulletin board.
Department of the Army Permit – 2000002188 (IP-AWP)
St John’s River Water Management District Permit – 4-035-18488-2
Contractor is required to inspect and maintain controls weekly and within 24 hours after a rainstorm in excess of 050 inches The contractor shall report all inspection findings and corrective actions taken as a result of the inspection. Inspection reports (650-040-03) shall be signed by the contractor and submitted weekly to the engineer at the progress meetings along with the name and certificate number of the person signing this form;
DEP- disposal of debris: Off-site contractor is liable even with a letter of approval from the property owner Contractor can request the DEP review the site and the Contractor needs to get a permit from the property owner to allow the area(s) to be filled;
Bill read a note concerning the dewatering operations at box culverts and wing walls. The specifications require a professional engineer prior to the start of construction submit a dewatering plan.
Notice of intent needs to be submitted by the contractor and any subcontractors that were involved in erosion operations.
Subletting Work: Bill noted that Willie Allen reviewed most of these items, however the forms listed are included in the handout package.
Procedures for subletting (provided in handouts)
Certification of Sublet Work (DOT Form 700-010-36), submit to Geneva Clarke in the District Office
No requests have been submitted yet?
List of subcontractors
Rental Agreements (DOT form 700-010-11)
Asphalt Paving – Tim McGlone , Resident Asphalt Specialist. Bill explained a pre-paving meeting will be held prior to the start of paving to review the items listed below.
Superpave asphalt
Asphalt mix designs
Pre-paving Meeting
48 hours notice given to CEI before any paving will be allowed.
Contract Time Tom White reviewed the time related issues listed below.
800 Days
Alternative Contract; A+B Contract with a maximum bonus amount of $2,500,00000.
Contract Daily Value $14,00000 for a maximum bonus time of 622 days.
Automatic work suspension days- if the contractor would like to work on any of these days they must submit a written request to work within 10 days of the automatic suspension days listed in Section 8-64 of the Supplemental Specifications. The engineer must approve the request; time will be charged regardless.
Weather Days – In accordance with 8-732 in the Standard Specifications.
One day of inclement weather = One day of time granted.
Dispute Review Board (DRB)
MacLaughlinFDOT Representative; Pete Markham
Contractor Representative; Jim
FDOT Representative and Contractor Representative have selected Don Henderson for the third representative. The Department will review this selection.
Partnering
The first partnering meeting is scheduled for today following this meeting with lunch at Chili’s. Joe Hartnett is the facilitator.
Construction Schedule / Progress Chart Submittals
CPM schedule is included in Superior’s package.
Curtis noted the paving will be night work as well as hauling embankment. All other activities will be done during daytime.
An updated schedule is required to be submitted on the Monday prior to estimate cutoff per 8-321.
Provide two-week look ahead schedules at the progress meetings.
If the time granted by Supplemental Agreement is 15 days or greater a Revised Schedule is required
Controlling Items of Work
No controlling item of work form will be necessary since this project has a detailed CPM schedule.
Vehicle Registration in Florida (DOT Form 700-010-52)
Was covered by Mr. Allen.
Contractor Past Performance Rating (CPPR)
Tom White noted the new CPPR form was included in the handout package. Superior has worked in the system on previous projects. Tom outlined how Superior would be informed of any problems or deficiencies.
Tom White reviewed the Special Project Requirements
Shop Drawing Schedule of Submittals (Due within 60 days of contract start) per 5-143
Tom White explained that all shop drawing submittals would go through Kevin Knudsen of Bowyer Singleton with a copy of the transmittal to RS&H CS.
Provide RS&H CS pavement marking readings of reflectivity per the specification.
Bill Downey outlined the New Equipment Specifications
Place a 2" minimum alphanumeric identification number on both sides of all equipment (other than small tools). Numbers should sharply contrast with background. This applies to prime and sub-contractor equipment;
Provide all trucks with numbers and certify that all trucks have a manufacturer’s certification or permanent decal showing the trucks capacity rounded to the nearest 1/10th of a CY. Provide a certified list at the Pre-construction Conference.
Request for partial payment for stockpiled material
Request for Payment for Stockpiled Materials (DOT Form 700-010-42) due with the required documentation on the Tuesday before a monthly cut off. Bill explained this was especially important if the material was not stored on site. If it was site stored, Thursday would be acceptable.
Signal Installation
In accordance with 611-5, the Contractor is required to provide a 90 day Warranty/Maintenance Bond prior to final acceptance;
Contractor to coordinate with the maintaining agency (Ray Marlin Flagler County) and the department’s representative prior to the final inspection.
Requested Documentation from Contractor
The following documentation were submitted at the preconstruction conference or were previously submitted:
¨
CPM Schedule.¨
List of subcontractors.¨
Lighting Plan showing the type and location of lights to be used for night work.¨
NPDES Contractor Certification.¨
NPDES Certification Preparation of Documents.¨
Asphalt QC Plan approved by the District Bituminous Engineer.¨
Vehicle Registrations (DOT Form 700-010-52).¨
Maintenance of traffic plans.¨
Emergency phone list.¨
ATSSA Worksite Traffic Supervisor name, 24 hr/day phone, certifications.¨
Letters to local police, fire and ambulance departments nearby the project.¨
Level II Concrete Plan.¨
Quality Control Plan.Handouts to Contractor
Contractor’s time extension request. (DOT Form 700-010-56)
Controlling Item of Work Plan. (DOT Forms 700-010-15)
CPPR (Discuss Rating Procedures)
Certification and Request for Payment for Stockpiled Materials. (DOT Form 700-010-42).
Monthly Estimate cut-off dates.
Certification of Disbursement of Previous Payments to Subcontractors. (700-010-38) (Due Monthly for Estimate)
Certification Compliance With Equal Employment Opportunity. (EEO) (DOT Form 700-011-13)
Construction Compliance with Specifications and Plans. (w/exemption examples) (Due Monthly for Estimate) 700-020-02
Contractor’s Certification of MOT Quantities. (log forms) (Due Monthly for Estimate)
Contractor’s Certification of Bituminous Materials. (Due Monthly for Estimate)
Maintenance of Traffic Review Report. (DOT Form )
QA (Quality Assurance) Guidelines (for information only) Located at the following website: http://wwwdotstateflus/construction/constadm/guidelist/coinspectguidelist/fy0304/coinspectguidelist0304htm ;
Procedures for subletting. (Certification of Sublet Work – DOT Form 700-010-36)
347 Concrete Specification
As directed in the contractor’s QC Plan.
Bridge Work still required
Pile Installation Plan.
Drilled Shaft Installation Plan.
The requirement for the District 5 Pre Pour meetings and Pre Drill meeting will be held in conjunction with our weekly meeting before the first pour or drilled shaft.
Monthly Estimates were discussed by Sean Heffernan
Sean explained that in genera the Cut-Off date was the third Sunday of the month, and a list of these dates was provided to the contractor. (provided in handouts)
By the Monday following cut off Sunday, the Certification of Disbursement of Previous Payments to Subcontractors due monthly for Estimate. (provided in handouts)
Construction Compliance with Specifications and Plans due monthly for Estimate is due at the same time. (provided in handouts)
Contractor’s Certification of MOT Quantities (log forms) due monthly for Estimate (provided in handouts) Due by noon following cutoff.
Contractor’s Certification of Bituminous Materials due monthly for Estimate. (provided in handouts)
Sean noted if there was any problem completing any of the forms to be sure and call him at the RS&H CS office.
Tom noted that the Public Information Officer at this time is Tom and Bill.
However, the Department plans on hiring a Public Information Officer part-time to handle issues with the public, area businesses, and lane closure announcements.
Progress Meetings
Meeting will be held on Tuesdays, at 10:00 AM at the RS&H CS field office with the first meeting to be on March 15, 2005.
Emergency Evacuation Plan
Tom White explained that since this roadway is a vital part of the evacuation route, there would need to be a plan to secure the project.
Other
Curtis noted the station boards are being placed throughout the project limits.
Spec 430-48 Final Pipe Inspection: Upon completion of all paving operations, dewater installed pipe(s) and provide the Engineer with a videotaping schedule. Provide the Engineer with a video tape of pipe(s) 48 inches or less in diameter for examination.
This is not Superiors first CQC project, so they are familiar with the program. They have also completed LIMS projects and have their user ID’s in place..
A Value Review Value Engineering Change Proposal (VECP) is in process concerning the temporary wall system.
Tom White discussed the actions to be taken if the Department receives an unpaid bill letter.
Tom asked when Superior felt the bridge crew would mobilize. They intend to begin the second or third week of the project.
Steve from the City of Flagler, asked if the connection of their new line could be postponed until they have completed a concurrent project that will allow many of their customers to remain in service during the change. A utility coordination meeting will be part of the first project coordination meeting.
There was no further business and the meeting was concluded at 10:48AM.
Respectfully submitted:
Thomas White, PE
Senior Project Engineer
Enc
|
Preconstruction Attendees |
|||
|
Name |
Company |
Phone |
|
|
Tom White |
RS&H CS |
386-673-7801 |
tom.white@rsandh.com |
|
Bill Downey |
RS&H CS |
386-673-7801 |
Bill.downey@rsandh.com |
|
Sean Heffernan |
RS&H CS |
386-673-7801 |
Sean.Heffernan@rsandh.com |
|
Ed Griffin |
RS&H CS |
386-673-7801 |
|
|
Deborah White |
RS&H CS |
386-673-7801 |
Deborah.white@rsandh.com |
|
Bhavin V |
Metric Engineering |
386-673-7801 |
|
|
Steve Homan |
FDOT |
386-943-5479 |
Steve.human@dot.state.fl.us |
|
Steve Nunnery |
FDOT |
386-254-3790 |
Steve.nunnery@dot.state.fl.us |
|
Morris Scott |
FDOT |
386-943-5356 |
Morris.scott@dot.state.fl.us |
|
Willie Allen |
FDOT |
386-258-4446 |
Willie.allen@dot.state.fl.us |
|
Chris Eggleston |
FDOT |
386-254-3730 |
Chris.eggleston@dot.state.fl.us |
|
Jennifer Vreeland |
FDOT |
386-943-5732 |
Jennifer.Vreeland@dot.state.fl.us |
|
Frank Smith |
FDOT |
386-740-3507 |
Frank.smith@dot.state.fl.us |
|
Mike Ruland |
FDOT |
386-258-4445 |
Mike.Ruland@dot.state.fl.us |
|
Shinji Konno |
FDOT |
386-943-5416 |
Shinji.conno@dot.state.fl.us |
|
Tim McGlone |
FDOT |
386-258-4444 |
Tim.mcglone@dot.state.fl.us |
|
Suzanne Phillips |
FDOT |
386-258-4449 |
Suzanne.Phillips@dot.state.fl.us |
|
Fred Henning |
Superior Construction |
904-945-4067 |
|
|
James Lewis |
Superior Construction |
904-237-9163 |
|
|
Shubhang Patel |
Superior Construction |
904-759-9917 |
spatel@superiorfla.com |
|
Cynthia Kelly |
Superior Construction |
904-292-4240 |
ckelly@superiorfla.com |
|
Pete Kelly |
Superior Construction |
904-292-4240 |
pkelly@superiorfla.com |
|
Curtis Long |
Superior Construction |
904-292-4240 |
clong@superiorfla.com |
|
Zach Mckenna |
Superior Construction |
904-292-4240 |
zmckenna@superiorfla.com |
|
Matt Schroeder |
Superior Construction |
904-221-9100 |
mschroeder@superiorfla.com |
|
Brian Davidson |
APAC |
904-219-9341 |
bdavidson@ashland.com |
|
Bruce Clark |
APAC |
904-878-9085 |
brclark@ashland.com |
|
John Taylor |
APAC |
904-288-6300 |
jwtaylor@ashland.com |
|
James Cooper |
APAC |
904-591-9462 |
|
|
Wayne Sweet |
APAC |
904-219-0408 |
kwsweat@ashland.com |
|
David Church |
APAC |
904-288-6300 |
dmchurch@ashland.com |
|
Dan Williams |
Safety Contractors |
904-255-6331 |
dawn@safetycontractors.com |
|
Pam Nagot |
Inwood |
407-971-8850 |
pnagot@inwoodinc.com |
|
Kevin Knudsen |
Bowyer Singleton |
407-943-5120 |
kknudsen@bsaorl.com |
|
Dale Polston |
Volusia Construction |
386-760-6111 |
Dpolston@volusiaconstruction.com |
|
Jerry Nix |
Volusia Construction |
386-566-2043 |
|
|
Phillip Honeywel |
Volusia Construction |
386-761-6111 |
pholliph@volusiaconstruction.com |
|
Stephen Flanagan |
City of Palm Coast |
386-986-2354 |
sflanagan@ci.palm.coast.fl.us |
|
Chris Johnson |
City of Palm Coast |
386-986-2354 |
cjohnson@ci.palm.coast.fl.us |
|
Keith King |
City of Palm Coast |
386-931-8009 |
kking@ci.palm.coast.fl.us |
|
Dick Rice |
City of Palm Coast |
386-986-9717 |
rrice@ci.palm.coast.fl.us |
|
Adam Biss |
Flagler County |
386-437-4116 |
abiss@myfcso.com |
|
Dennis Creamer |
Flagler County |
386-437-7381 |
dcreamer@fcbcc.org |
|
Bruce Stephenson |
FPL |
||