SR 79 Widening Project 

Schedule

Begin Time August 31, 2007
Start Construction September 10, 2007
Original Contract Duration 815 Days
Begin Driving Bridge Test Piles - Pine Log Creek Bridge February 14, 2008
Completed Driving Production Piles - Pine Log Creek Bridge April 30,2008
Begin Placing Beams on Northbound Bridge June 5, 2008
Traffic Switch June 18, 2008