| Begin Time | August 31, 2007 |
| Start Construction | September 10, 2007 |
| Original Contract Duration | 815 Days |
| Begin Driving Bridge Test Piles - Pine Log Creek Bridge | February 14, 2008 |
| Completed Driving Production Piles - Pine Log Creek Bridge | April 30,2008 |
| Begin Placing Beams on Northbound Bridge | June 5, 2008 |
| Traffic Switch | June 18, 2008 |