I-95 Widening from SR-528 to Fiske Blvd.
FDOT project number 405506-5-52-01
FDOT contract number E5K74

Location
Click to see a larger image.
Updated 07/15/09
This $148,000,000.00 dollar contract is for adding lanes to
I-95 from SR-528 to Fiske Blvd. The
contract time is 950 days including the design and construction. The project started
on March 01, 2007. The original project completion date was November 29, 2009.
This date has changed due to delays from weather, hurricanes, and unexpected
delays. Currently the contract time is 1035 Days with a final date of
December 29, 2009.
Kiewit Southern Co., Inc is the general contractor. The
contract contains a bonus provision for early completion of the work. The
bonus is paid at the rate of $15,000.00 for each day the project is finished
prior to 10/4/09 to a maximum of $3,630,000.00. The
project length is 10.13 miles. Project completed on July 14, 2009.