I-95 Project Photo Page 6   Project nearing completion

exposed bar.jpg (103037 bytes) locations.jpg (100670 bytes)
The paver malfunctioned and placed reinforcing steel too close to the surface of the roadway. This occured in may locations requiring the removal of some of the slabs.
sawing.jpg (74196 bytes) slab removal.jpg (103290 bytes)
First the slabs were saw cut. Then the pieces were removed.
slab removal bad.jpg (119358 bytes) grading.jpg (108708 bytes)
The excavation was cleaned up, and graded.
asphalt.jpg (72833 bytes) Dowels.jpg (104797 bytes)
The one inch thick asphalt layer was replaced. The dowel bars were re-drilled.
ATPB.jpg (159320 bytes) finished.jpg (60893 bytes)
The drainage layer replaced. And the slab was re-poured.
Looking south in median.jpg (78088 bytes) North end 12 08.jpg (68125 bytes)
The finished product looking south, south of SR-520. North end of project with final grading done, and pond I-4
curve 3 12 08.jpg (60737 bytes) 12 08 air.jpg (68889 bytes)
Final grading a sod complete the new Wal-Mart under construction at SR-520